167963 - Major overhaul of Steam Turbine FFA10 in 2024 Tender

The deadline for applying for prequalification for the project has been exceeded.

Description

Fjernvarme Fyn Affaldsenergi (FFA) is located Havnegade 120, DK-5000 Odense C, only a few kilometres from the city centre.

The power plant consists of a coal-fired CHP unit 7, a straw-fired CHP unit 8 and a waste incineration plant with three waste-to-energy boilers (Line 11, Line 12 and Line 13) providing steam to two steam turbines (FFA10 and FFA13).


FFA10 is a waste fired CHP plant. It was commissioned in 1996 and has a capacity of 11/13 MW electricity and 29 MJ/s district heating.

The steam turbine is planned to be in operation until 2032 (as a minimum).


The scope of supply for this tender is a major overhaul of the FFA10 steam turbine, gear and generator.


The main target with the major overhaul is to ensure that the unit is in a condition where it can be operated safely, reliably and efficiently until the next major overhaul.


Tender procedure

Negotiated procedure

The Contracting Authority / Contact details

Fjernvarme Fyn Service A/S
Havnegade 120
5000 Odense C
Note stated for this project

Documents

0
No publicly accessible documents have been added

Disciplines

  • Repair and maintenance services
  • Turbine installations
  • Steam turbines
  • Parts of turbines
  • Parts of steam turbines
  • Turbine works
  • Installation services of steam generators, turbines, compressors and burners
  • Installation services of turbines